Granite Announces Caldwell Avenue Interchange Reconstruction Project on SR99 in Visalia, California
The project scope includes the construction of two new precast girder bridges: a two-span structure over SR99 and a single-span structure over the UPRR tracks. Additionally, 12 new retaining walls will be built, featuring cast-in-place concrete, mechanically stabilized earth (MSE) walls, and soldier pile walls with timber lagging. To further enhance accessibility, four new on/off ramps will be constructed, with traffic being controlled by new roundabouts at each set of ramps.
“Our team is committed to enhancing infrastructure and improving safety for our community and the traveling public,” said Jeff Grimm, Granite Area Manager. “This project is near another pavement rehabilitation project in
Approximately 216,000 cubic yards of import borrow will be used to widen the embankments for the expanded roadways on either side of the new bridges. The project also includes upgrades to drainage systems, installation of pavement delineation and roadside signage, and replacement of highway electrical items.
Construction is expected to begin in August 2025 and be completed in Q2 2027.
About Granite
Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in
View source version on businesswire.com: https://www.businesswire.com/news/home/20250306705161/en/
Granite Contacts
Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861
Source: Granite